115H601 115kV H-Frame Double Circuit Tangent
Revision 1
Dec 26, 2023
- Pole must be set so that pole tops are level, while maintaining minimum pole settings depths per District standards or as noted on the construction drawing. Refer to T&D Guideline 4-5-15.0.
- Engineer must specify the size & number of down guys and anchors depending on conductor design tension, line angle, available down guy lead and span length. Refer to T&D Guideline 4-6 and Compatible Unit Sections A and G.
- Outermost structure down guys must be splayed so as to provide a minimum of 3' clearance from the innermost structure. Refer to picture below.
Compatible Unit | Description | Quantity |
---|---|---|
I0706 | Insulator, Horizontal Post 115kV Polymer 49" Nominal | 2 |
I0707 | Insulator, Horizontal Post 115kV Polymer | 2 |
MS2302 | Rock, Crushed 5/8” Minus, 5/8” and 3/4” | 2 Cu Yd |
R1007 | Clamp, Line Post Insulator 795 - 1272 kcmil | 6 |
R1501 | Cross-Brace, H-Frame 115kV | 1 |