12F421 - 1Ø Volt-Meter Installation

Revision 7
Dec 29, 2017

Notes:

  1. Transformer is dedicated to the volt-meter installation and serves no other load.
  2. Refer to 12F601 for details on transformer mounting.
  3. Install connections to common neutral from ground wire, transformer case ground, primary and secondary neutrals.
  4. Do not remove transformer case ground unless cutout is open.
  5. When installing a new pole that requires a ground, a ground plate is preferred over a ground rod. For ground plate installation see Compatible Unit N0110.

 

Material List

Compatible Unit Description Quantity
BA21C Transformer, OH 1.5 kVA 7.2/12.47kV - 120/240 1
D0101 1Ø Volt Meter Installation 1
E0202 Cutout, 100A 15kV Open Loadbreak Type 1
N0110 Ground Plate Installation on Wood Pole 1
R0102 Crossarm Mount w/ 3/8" x 6" Carriage Bolts (For Standard 7', 10', 11' & 13' Crossarms) 1
Z010* Clamp, Hotline Al 1
Z060+ Connector, H-Type Al Compression 4
Z0672 Connector, Mini Wedge 2